Modifying the Power Schedule to affect all associated instances

I have an instance named “Test-instance”
I have a power schedule named “Test-schedule”
The “Test-schedule” is assigned to “Test-instance”

The instance is automatically starting and stopping according to the power schedule. For example, on Monday, the instance is scheduled to start at 7 AM. However, if the user later decides to change the schedule to start at 9 AM, even after modifying the power schedule at 8 AM, the instance does not stop until the user manually goes to that instance, selects “Edit”, and save.

Current behavior is that it seems to cache the power schedule until you modify the instance or the next triggered schedule action like shutdown at 5pm and then it will power on at 9am the next day based on the new schedule. Also possible that Morpheus refreshes the cached schedule in the middle of the night.